How to Implement Accurate Skills Planning
Learn how employee skills support better project staffing. Read Can Do’s English introduction to the Computerwoche ...
Explore the platform for project and multi-project management in a personal demo.
7 min read
Conny Düran
:
11.10.2024
Updated on
In companies running several projects in parallel, capacity planning is one of the central challenges of project management. In engineering in particular, projects often compete for the same specialists. Design engineers, development engineers and technical specialists are needed on different projects – often at the same time and under considerable time pressure.
Simply comparing available working hours with planned project effort is not enough. What matters is whether the right people with the required qualifications are available at the right time.
Realistic capacity planning must therefore consider both individual employees’ workloads and the requirements of all current and planned projects. Rolling planning complements this approach by enabling long-term planning without having to define every task and date in detail at the outset.
In practice, people rarely work exclusively on a single project. A development engineer, for example, may be working on an ongoing product development project, supporting a customer project in parallel and also be needed to assess the technical aspects of a new initiative.
Each project manager initially considers the requirements of their own project. An employee’s actual availability, however, only becomes clear when all their commitments are taken into account.
This creates typical challenges:
Considering individual projects in isolation therefore often leads to unrealistic resource utilisation plans. Only a capacity overview across projects shows which resources are actually still available and where bottlenecks may occur.
The foundation of any capacity plan is employees’ actual availability.
An employee working a 40-hour week theoretically has 160 working hours over four weeks. However, not all these hours are available for planned project work.
Several factors must be considered when calculating available capacity.
Full-time and part-time work, individual working arrangements and regional public holidays affect available working time. Annual leave, sickness and other absences must also be taken into account.
Reliable resource planning incorporates this information automatically wherever possible. This helps avoid scheduling employees during planned absences or assigning too much capacity to part-time staff in project plans.
Alongside project work, many specialists carry out regular activities such as technical coordination, support, internal meetings or administrative tasks.
This baseline workload reduces the capacity available for projects and must be accounted for in planning.
The next step is to include the planned effort from all ongoing projects.
In simplified terms, remaining capacity is calculated as follows:
Available project capacity = working time minus absences, public holidays and baseline workload
Free project capacity = available project capacity minus effort already planned for projects
Take care not to deduct absences and public holidays again if they are already accounted for in the underlying working time.
This calculation provides an initial indication. Whether additional project work can actually be scheduled also depends on the qualifications required and when the tasks need to be carried out.
One of the most common misconceptions in resource planning is that enough spare hours automatically allow a company to commit to another project.
This is particularly problematic in engineering. Technical tasks often require specific knowledge, experience or certifications. An employee with spare capacity therefore cannot necessarily take over the tasks of a specialist who is already fully allocated.
A company is working on several development projects in parallel. An additional customer project requires the following work within the next four weeks:
| Task | Effort | Required qualification |
|---|---|---|
| Technical design | 40 hours | Design engineer |
| Technical review and approval | 16 hours | Qualified review engineer |
| Total requirement | 56 hours |
The resource plan shows a total of 80 hours of spare capacity for this period.
At first glance, the new project appears straightforward to deliver.
A closer look, however, reveals the following:
Although there is enough spare capacity overall, there is a shortfall of eight hours of a specific qualification when it is needed.
The project therefore cannot proceed as planned under the existing conditions.
What options are available?
The company can postpone the technical review, reschedule the review engineer’s existing tasks or assign another qualified employee.
Each of these decisions may affect other projects.
This illustrates the difference between a simple overview of hours and integrated resource and multi-project planning: It is not just the calculated workload that matters, but also whether the work is feasible in terms of timing and expertise.
In many engineering projects, planning spans several months or even years. At the start of a project, not all work packages, their precise effort or their dates are known.
Nevertheless, companies need to assess future resource requirements early.
If capacity planning only included fully defined tasks, a large proportion of future resource demand would initially remain invisible. This could lead to capacity being allocated more than once or new projects being accepted on an unrealistic basis.
It therefore makes sense to plan long-term resource requirements at a higher level first.
For example, a future development phase might require 200 hours of design work and 80 hours of technical review, without specifying every individual step yet.
The plan then shows early on which qualifications will be needed and when.
However, it is important to distinguish between a planned resource requirement and a confirmed staffing allocation. A high-level capacity reservation does not yet mean that the required employees will actually be available later.
Rolling planning connects long-term capacity planning with increasingly detailed project planning.
The basic principle is simple: The closer a project phase gets, the more precisely its tasks, effort and resources are planned.
For phases further in the future, a high-level estimate of resource requirements is initially sufficient. Work coming up soon, by contrast, is planned in detail and assigned to specific employees.
A development project is scheduled to run for twelve months.
At the start, the individual phases and their expected resource requirements are planned. Specific work packages are already in place for the next four weeks, while later project phases are initially included using estimated effort only.
As the project progresses, the upcoming phases are developed in more detail. The original high-level resource requirements become specific tasks with defined dates and responsibilities.
It is essential that capacity already accounted for is not counted twice in the plan.
If, for example, 200 hours were planned for a project phase and 80 hours have since been converted into specific tasks, 120 hours remain for further detailed planning, provided the total requirement is unchanged.
If new information leads to higher or lower effort estimates, that change must be reflected in the overall capacity plan.
This approach allows companies to account for long-term resource requirements without implying a level of precision that is not yet possible in practice.
At the same time, planning remains flexible. New insights from project delivery are incorporated continuously, making changes in resource requirements visible.
This is particularly relevant to development projects, where technical requirements, task durations and project priorities may change over time.
A resource plan rarely remains unchanged throughout a project’s entire lifecycle.
New customer orders, changing priorities, schedule shifts or unexpected additional effort can significantly affect the original plan.
In multi-project management, it is therefore not enough to consider a change only within the project directly affected.
For example, moving a development milestone by two weeks may mean that the required design or review engineers are scheduled to work on another project at the same time.
A schedule change may thus create a resource conflict that did not exist in the original plan.
To make an informed decision, the impact on all affected projects must be visible.
Project managers and resource managers need a shared information base covering both existing commitments and future resource requirements.
Rolling planning ensures that this information is updated regularly. Suitable multi-project management software also helps identify bottlenecks and potential overloads early and assess alternative plans.
The more projects, employees and dependencies there are to consider, the harder it becomes to plan capacity reliably using separate spreadsheets or isolated project plans.
Can Do brings the relevant information together in shared resource and multi-project planning.
Individual working time models, public holidays, annual leave and other absences provide the basis for calculating available resources.
Baseline workloads and project effort already planned can also be included. This creates a view of resource utilisation across projects.
It is not always clear yet which employee will take on a particular task.
With Can Do, resource requirements can initially be planned based on the skills needed. Specific employees can be assigned later.
This allows future skill requirements to be included in planning early.
Can Do supports planning with uncertain timeframes and estimated effort.
This is particularly useful for long-term projects whose tasks and dates will only become more specific as the project progresses.
Resource planning can therefore begin before every project detail has been established.
Can Do’s Watermodel® algorithm simulates the distribution of parallel tasks within the planned timeframes.
This goes beyond looking at the total number of planned hours. Overlapping tasks and the resulting workload risks can also be assessed.
In addition, AI assistance can suggest suitable alternative employees based on their qualifications and availability. The decision to make an actual planning change remains with the people responsible.
In this way, Can Do helps project managers and resource managers make planning decisions based on traceable data.
Suitable software should do more than display employee utilisation or compare available and planned hours.
The following functions are particularly important for companies with complex development projects:
Crucially, these functions must not operate in isolation. Only by working together do they enable a realistic assessment of available capacity and the feasibility of new projects.
Successful capacity planning does not just answer the question of how many working hours remain available. Above all, it shows whether the required qualifications can be deployed during the right period without putting other projects at risk.
Rolling planning provides the necessary link between long-term resource planning and short-term task management. Future requirements are accounted for early and refined as the project progresses.
For companies running several projects in parallel, integrated resource and multi-project management software is therefore an essential foundation for planning capacity realistically, identifying bottlenecks early and making informed project decisions.
Discover in a personal Can Do demo how to plan resources across projects and reliably assess the feasibility of new projects.
Conny Düran is Head of Customer Service and Support at Can Do. She is therefore very close to the challenges of the prospective customers and the everyday project work of the users. In the Can Do blog, Conny writes about features of our software that are particularly popular with users.
Learn how employee skills support better project staffing. Read Can Do’s English introduction to the Computerwoche ...
Explore portfolio systems, simulation and project approval in Can Do’s three-part project portfolio management series. ...
Archive: Can Do announced its Can Do Hours app for AI-supported time tracking and task planning at DIGICON 2018. Read ...